Critical Path

The critical path is the longest duration path through a schedule network. Its activities typically have zero total float in an unconstrained model, so their delay can move the forecast completion date. Imposed dates or other constraints may produce positive or negative float.

Calculate it from dependencies and duration estimates, then monitor near-critical paths as conditions change. The result is only as reliable as the schedule logic and assumptions behind it.