Assess and Implement Changes

This process manages project changes that may affect multiple aspects of the project and adjusts plans based on stakeholder recommendations throughout the project life cycle.

Changes are considered as integrated decisions so their effects on objectives, commitments, and performance domains remain visible.

Key inputs: Change proposals, stakeholder recommendations, impact analysis, current plans, constraints, risks, and approval thresholds.

Activities:

  1. Clarify the proposed change, its intended outcome, and the reason it is needed.
  2. Assess impacts across plans, performance domains, stakeholders, and obligations.
  3. Compare alternatives, including rejection, deferral, or a smaller change.
  4. Obtain the required decision using delegated approval authorities.
  5. Update affected plans and communicate the authorized change.
  6. Implement the change and verify its intended effect.

Outputs: An approved, rejected, or deferred change decision; adjusted plans; assigned actions; and implementation evidence.

Governance check: Have all material consequences been assessed and reflected in the adjusted plans?