Work Breakdown Structure
A work breakdown structure (WBS) decomposes the total project scope into smaller, deliverable-oriented components. Its lowest controlled level is commonly called a work package.
Build the WBS around outcomes or deliverables rather than an unstructured task list. Apply the 100 percent rule: together, child elements should represent all of the parent scope without adding unrelated work.