Earned Value

Earned value management compares planned value (PV), earned value (EV), and actual cost (AC) at a reporting date. Schedule variance is EV−PVEV - PV, while cost variance is EV−ACEV - AC.

Indices such as SPI=EV/PVSPI = EV / PV and CPI=EV/ACCPI = EV / AC support trend analysis and forecasting. The method requires a credible baseline and objective rules for crediting completed work.